F1 is one sport that every fan terms as crazy when he hears the roar of the engine. Indian fans are set to get a taste of ..
Coalgate scam: Restore Coal India to commanding heights

The Comptroller and Auditor General (CAG) of India tabled three
reports in Parliament on Friday 17 August 2012 indicting the
Congress-led UPA government for having caused major losses to the
state through its policies on power, coal and aviation, totalling
up to a humongous sum of 3.8 Lakh Crores. According to the figures
provided by the CAG, the Coal mining scam is even bigger and
shoddier than the infamous 2G scam, where at least some of the
benefits were passed on to the final consumers in the form of
increased competition and lower call charges. But that was not the
case with unused coal blocks, which did not increase availability
of coal, or lower the price of power or steel.
After coal nationalisation in 1973, the public sector Coal India
Limited (CIL) was given exclusive rights of coal extraction in the
country. But due to the increasing demand for coal after 1991 in
the power, steel, and cement sectors, Coal India could not keep up
with the increased demand without expanding its operations.
Consequently, to boost coal production, the government decided to
go for selective allocation of coal blocks (instead of competitive
bidding) to a few major end-users in the public and private
sectors, for captive use. This raises the legitimate question – why
was a financially flush Coal India not allowed to expand its
operations? Why weren’t more coal blocks allotted to CIL?
The CAG report narrates how the government favoured and benefitted
private players through its policies. The report says that coal
fields in the period 2004-2009 were allocated to private entities
instead of being auctioned. This obscure allotment has resulted in
an 186,000 Crore benefit to private players. The CAG report has
bought Prime Minister Dr. Manmohan Singh under scrutiny as there
are serious discrepancies during the period when he was in-charge
of the coal portfolio. As coal minister, he is alleged to have
allotted over 40 billion tonnes of coal at throwaway prices. The
Prime Minister’s Office has also been bought under scrutiny as it
delayed introducing the process of competitive bidding, though
cleared by the Law and Justice Ministry.
Though the method of calculation of loss by the
CAG has been criticised by ‘analysts' on several grounds, whatever
the ‘true’ estimate, there is no doubt that there has been a
substantial loss to the nation and the CAG has bought it
out.
The CAG has named companies including Essar Power, Tata Steel, Tata
Power and Jindal Steel and Power which have got the blacks in
various states. It says the Anil Ambani-owned Reliance Power
Limited (RPL) has been a major beneficiary; that the government
conferred Rs. 29,033 Crore in “undue benefits” to RPL as it allowed
RPL to use surplus coal from the blocks allotted for the Sasan
power project for its other plants. The Government and the Congress
party have already come out with a defence saying that the alleged
loss is an inaccurate figure as the CAG has taken only general
figures and not mine-to-mine. Yet, if the CAG did take on such a
huge task of calculating losses mine-to-mine, it would not result
in a clean-chit to the government’s opaque policy making.
Where Government has been caught in a tangle is the fact that after
being allotted the captive mines at scrap prices, many private
entities sold these companies (or partial equity) at huge premiums,
while some actually sold coal in the open market in utter violation
of contract stipulations. Coal mine allocation was done to augment
the country’s coal output and ensuring uninterrupted fuel supplies
to power plants. The whole purpose of allowing captive mining and
expediting allocation of blocks was to boost production in the
short to medium run (which did not happen).
In the light of coal shortage and pushed by private power
producers, the Centre has been pushing CIL hard to sign Fuel Supply
Agreements (FSAs) and minimum supply guarantee. The Prime
Minister's Office (PMO) has been pushing hard for signing FSAs, to
the extent that it even had a presidential directive issued to
bring CIL to the table and sign said FSAs with projects ready by
December 2010 and/or those to be commissioned by March 2015, and
have long-term power purchase agreements in place. But opposition
from independent directors and dispute with power producers over
certain clauses has held up these agreements.
IIM-Ahmedabad director Samir Baruah, an independent director on the
CIL board, has now raised a big question – is the government
extending double benefits to some private players by forcing CIL to
sign fuel supply agreements (FSAs) with those who have already been
allotted captive blocks for their production needs?
“It would be myopic for (CIL) board to believe that coal-gate has
nothing to do with signing of FSAs. FSAs are clearly designed to
bestow favours to chosen projects and producers of power. If they
also appear to be those who received largesse from the government
in terms of allotment of coal blocks then we would also be guilty
of favours to the same set of projects/owners,” Baruah wrote in an
e-mail to CIL company secretary M Viswanathan on August 28. The
question followed Government’s unusual step of issuing a
presidential directive to CIL to sign FSAs with power projects
guaranteeing to supply 80% of the contracted quantity or pay hefty
penalty to project promoters. The directive was issued after the
six independent directors, including Baruah, had blocked the FSA,
doubting CIL's capability to meet the minimum supply guarantee.
(link)
The real scam, therefore, is less about the monetary loss, but more
about the mines being allocated to seeming end-users for captive
requirements, and these users, who got the blocks cheap with hardly
any penalties for not meeting production milestones, rather than
producing coal were simply squatting on the mines (for windfall
gains later). The CAG report states that mining was undertaken only
in 28 out of the 86 captive coal blocks that were scheduled to take
up production, and they failed to produce even half of what was
targeted from those blocks.
CAG states that the delay in introduction of the process of
competitive bidding has rendered the existing process beneficial to
the private companies. The audit estimates financial gains to the
tune of 186,000 Crores likely to accrue to the private players. The
CAG also said that a part of this gain could have accrued to the
exchequer by the introduction of competitive bidding. The concept
of allocation of captive coal blocks through competitive bidding
was announced in 2004, but government has still not finalised the
modus operandi of competitive bidding.
Conclusion : Though the initial agreements signed
with those allotted mines had clauses that the coal blocks would
have to be returned if production deadlines were not met, the
government did not enforce these clauses.
Government must now salvage the mess by taking back the coal blocks
from those who have either been squatting on the resource, or have
been selling the coal in the open market, or have sold equity at
premiums (which suggests the true value of the resource acquired
cheap), and impose heavy fines. These blocks and captive mines
should be re-allocated only through the process of transparent
competitive bidding. Or simply handed over to Coal India.
The government has been pushed to the limits, having even
considered a vote of confidence, as the Opposition stalls the
proceedings of Parliament. The mood of the nation inclines towards
a mid-term poll, and the ruling coalition is well aware of this
fact. Many key UPA allies can be seen actively preparing for
mid-term polls and may even be ready to ditch the Congress and form
a Third Front should the NDA fail to produce substantial numbers in
the polls.
First Published | Follow twitter.com/vijayvaani
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - -
Author : Rijul Singh Uppal | Follow writer at twitter.com/therijuluppal
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - -
Share Your View via Facebook
top trend
-
Behind the scenes at F1: A preview of the biggest party in town
-
Modi rocked, Gehlot shocked: NRI Conference
Gujarat Chief Minister Narendra Modi outshined others in Pravasi Bharatiya Sammelan at Jaipur. The joint session was pa..
-
Guilty, until proven innocent - A note on Mayaben Kodnani's conviction in Gujarat Riots
The Naroda Patiya riot case involved a matter of national importance and it is a case that had been tremendously debat.. -
Can The Congress' Propaganda Cover-up MMS Scams?
By Titu Shadowson
The recent growth in MMS scandals can be explained sarcastically: this nation is run by.. -
Volunteers urge Anna to restart apolitical movement for Janlokpal
The voice of continuing the anti-corruption movement demanding Janlokpal is gaining more support from different quarters..
what next
-
-
"Coal allocations since 1993 are arbitrary and illegal", Says Supreme Court
-
Palestine, 6 billion people and second hand opinions
-
Malegaon 2006 vs. Malegaon 2008 - Blast Politics
-
Who will investigate Chidambaram & Co for the Dabhol Loot?
-
Narendra Modi prepares to climb the ramparts of the Red Fort
-
The Great Jindal Swindle
-
AAP's insidious anti-Hindu agenda
-
Nagma - Sonia Gandhi's Star Soldier
-
Aam Aadmi Party : Anti-Modi stalking horse
-
What in God's name is Teesta Setalvad's agenda?
-
-
-
Time to rethink : Saffron surge and the secular debacle - Sri Sri Ravi Shankar
-
India's Wishlist for Prime Minister Narendra Modi
-
My first meeting with Narendra Modi - Sri Sri Ravi Shankar
-
Telangana - Divide and Rule?
-
Myths vs Facts about RSS
-
The Two States: Telangana and Seemandhra
-
Answering Media on Questions to Narendra Modi, but will they venture into responding these queries?
-
#AAPCon : Dilli ke log ban gaye Mamu
-
Secularism is just synonymous with Sanatan Dharm
-
Beware of the Hoax called Aam Aadmi Party
-
Comments (Leave a Reply)